Gantt Chart for a Patient Satisfaction Survey

Ten items over nine months at one practice. A chart of ten bars that could all start on day one has not modelled the project at all.

Editorial process

Last reviewed · August 16, 2026

01

Ten items over nine months, and the dependencies are the content

A Gantt chart is only worth drawing if it encodes dependencies, and that is the difference between a plan and a decorated list. Ten items over nine months at one physician practice means each task averages a few weeks, so the granularity is at the level of 'design the instrument', 'pilot with twenty patients', 'train front desk staff' rather than 'do the survey'. What makes it a project plan is that some of those cannot start until others finish: you cannot pilot an instrument you have not designed, cannot train staff on a process you have not finalised, and cannot analyse data you have not collected. Others can genuinely run in parallel — securing leadership sponsorship, checking whether the organisation already collects comparable data, and preparing the analysis plan can all happen while the instrument is being drafted, and showing that overlap is what makes nine months feasible.

Two things separate a strong submission. First, work backwards from the goal: the point is improved patient satisfaction, not a completed survey, so the last items on the chart should be feeding results back and acting on them rather than producing a report. A chart that ends at data collection has modelled a measurement exercise and missed the assignment's own framing. Second, put slack somewhere visible. Nine months is comfortable for this scope, which means the plan should show where the float sits and which items are on the critical path — the sequence where a delay pushes everything after it. Name your milestones as decisions rather than as dates: instrument approved, pilot complete, collection closed, findings presented. And read the case for its own obstacles, since the assignment expects your chart to respond to what went wrong at Leonard-Griggs rather than to a generic rollout.

Likely learning objectives

Inferred from the brief — check these against your own rubric.

  • 01
    Decompose a project into tasks at an appropriate granularity.
  • 02
    Identify dependencies and distinguish sequential from parallel work.
  • 03
    Locate the critical path and where slack exists.
  • 04
    Extend the plan past measurement to the improvement it is meant to produce.
Assignment instructionsQuoted verbatim

Read the full question

Review every instruction before using the planning guidance that follows.

In this assignment, you will have the opportunity to use a project planning tool to show how you will use information and imagination to show the project components for implementing a survey process at a physician facility. Review the Rocky Road to Patient Satisfaction at Leonard-Griggs case on pages 423-425 of your textbook. Create a Gantt chart (as in Exhibit 3.7 on page 72 of your textbook) for that project to show the timeline for implementing the survey at one of the physician practices. Your Gantt chart should have at least ten items in place, working to achieve the goal of instituting a survey to improve patient satisfaction over a nine-month period. 1- 4 pages not including the first and the reference 2- Zero plagiarism 3- APA writing guiding style You are strongly encouraged to submit all assignments to the Turnitin Originality Check prior to submitting them to your instructor for grading
02

Turn the brief into deliverables

  1. 01
    A Gantt chart with at least ten items over nine months.
  2. 02
    Durations for each task.
  3. 03
    Dependencies shown, with parallel work identified.
  4. 04
    Named milestones.
  5. 05
    Tasks extending to feedback and action, not only collection.
  6. 06
    1-4 pages plus references, in APA style.
03

Tasks, durations, dependencies, milestones

01

What the case tells you

Extract the obstacles Leonard-Griggs actually encountered.

02

Task decomposition

Break the project into ten or more items at a workable granularity.

03

Durations and dependencies

Assign durations and identify what blocks what.

04

The critical path and slack

Identify where a delay propagates and where float exists.

05

Milestones

Define decision points rather than calendar markers.

06

From data to improvement

Include feedback, action and re-measurement in the timeline.

04

Project planning and survey implementation guidance

Recommended databases

  • Project Management Institute
  • AHRQ CAHPS resources
  • The assigned textbook exhibits
  • PubMed Central

Search sequence

  1. 1.
    Read the case before drafting; the assignment expects a response to it.
  2. 2.
    Check the Exhibit 3.7 format so the chart matches what was asked for.
  3. 3.
    Look up patient satisfaction survey implementation guidance for realistic durations.
  4. 4.
    Find evidence on what makes satisfaction data actually change practice.
05

Reference shortlist

These are authoritative starting points, not a ready-made bibliography. A qualified reviewer must confirm that each source fits the assignment and supports the claim beside which it is cited.

Nothing here is cleared for citation until you have read it.

  1. 01

    What is Project Management?

    Project Management Institute · 2024

    The project management framing behind task decomposition and dependency.

  2. 02

    Stay informed with our Standards & Publications

    Project Management Institute · 2026

    Where scheduling and planning practice is codified.

  3. 03

    Section 4: Ways To Approach the Quality Improvement Process

    Agency for Healthcare Research and Quality · 2024

    How survey findings become an improvement cycle — the tail of your chart.

  4. 04

    17.2 The Planning Process - Principles of Management | OpenStax

    OpenStax, Rice University · 2019

    The planning process, for the sequencing logic behind the chart.

  5. 05

    17.3 Types of Plans - Principles of Management | OpenStax

    OpenStax, Rice University · 2019

    Types of plans, useful for distinguishing the project plan from the standing process.

06

Review before submission

Common mistakes

  • Drawing ten bars with no dependencies between them.
  • Setting granularity too coarse, so the chart has nothing to sequence.
  • Ending the chart at data collection rather than at improvement.
  • Ignoring the case's own obstacles when building the plan.

Submission checklist

  • Does the chart show at least one dependency chain three tasks deep?
  • Is any work genuinely parallel?
  • Are the milestones decisions rather than dates?
  • Does the plan reach acting on the findings?

Use this guide to plan and review your own work. Follow your institution's rules and read our academic-integrity policy.

Written by

Aaron Bishop

MA, Education

assignment interpretation and research-methods coaching across disciplines

Aaron leads the EssayCrackers editorial desk. He works on how assignment briefs are read — what a rubric is actually asking for, and where students most often answer a different question than the one set.

Reviewed by

Dr. Nathan Cole

PhD, Rhetoric & Composition

Argumentation and thesis development

Nathan teaches first-year composition and directs a university writing center. He reviews EssayCrackers guides for argumentative soundness and citation accuracy.

Want feedback on your plan before you draft?

Get help interpreting the brief, checking your evidence strategy, and strengthening your outline while keeping the work your own.

Get assignment guidance
Start your order